Construction Projects


Capital_Project_2021_Map

Find out what is happening on current construction projects:

  • 62 Street
  • 2021 Asphalt Overlays
  • 2020 Asphalt Overlays
  • 56 Street and 50 Ave Traffic Signals
  • 2021 Sidewalks
  • CCTV
  • 55 Avenue
  • 2021 Pavement Markings
  • Public Works Shop Renovation & Addition
  • 40 Ave & 53 St Traffic Signals

62 Street Reconstruction

Description

This reconstruction will include relocation of shallow utilities, rehabilitation of the ditches, replacement of culverts, raising the roadway elevation, rebuilding the road base, and an asphalt surface. The ditch and culvert rehabilitation will extend north along the 62 Street right of way to the 50 Avenue right of way.

Location(s)62 Street, 49 Avenue, and Evergreen Close
Estimated Start DateJune 21, 2021
Estimated Completion DateSeptember, 2021
ConsultantMcElhanney Ltd.
ContractorNu Edge Construction Ltd.
Road ClosuresTo be determined
Temporary Utility ShutdownsNone Anticipated
Other Information


2021 Asphalt Overlays

DescriptionThis project will allow for resurfacing of 52 Street between 47 Avenue and 49 Avenue. It will also inlcude resurfacing of the Curling Rink Parking Lot. 
Location(s)

52 Street from 47 Avenue to 49 Avenue

Curling Rink Parking Lot

Estimated Start DateJuly 30, 2021
Estimated Completion DateSeptember 30, 2021
ContractorBorder Paving Ltd.
Road ClosuresNo road closures. However, there will be various construction and/or work zones as required. Please use caution when driving past construction zones. 
Temporary Utility ShutdownsNone
Other Information


2020 Asphalt Overlays

DescriptionThis project will allow for resurfacing of 40 Avenue between 56 Street and the Reynolds Alberta Museum along with a final layer of asphalt on 48 Street leading into the southeast industrial area. Paving will be followed by inlaid thermoplastic line paint that is expected to last 5 - 10 years. This years program is being funded through the Alberta Governments Municipal Stimulus Program. 
Location(s)

40 Avenue from 56 Street to the Reynolds Alberta Museum

48 Street south of 37 Avenue (South East Industrial Road)

Work DatesSeptember 22, 2020 - November, 2020
Spring 2021
ContractorCentral City Asphalt
Road ClosuresNo road closures. However, there will be various construction and/or work zones as required. Please use caution when driving past construction zones. 
Temporary Utility ShutdownsNone
Other InformationThe utility repairs are completed.

The North bike path on 40 Avenue  from 56 Street to 64 Street is complete.

The southeast industrial road (48 Street) Is complete

Paving on 40 Avenue from 56 Street to the Reynolds Alberta Museum is completed.

Line painting and final landscaping will be completed shortly. 

56 Street & 50 Ave Traffic Signals

DescriptionThis project will remove and replace the existing traffic signals at 50 Ave & 56 Street.
Location(s)50 Avenue & 56 Street Intersection
Estimated Start DateSpring 2021
Estimate Completion Date Fall 2021
ContractorHighLine Electrical Constructors Ltd.
Road ClosuresPlease follow all posted signage and use caution when driving through construction zones.
Temporary Utility ShutdownsNo
Other

2021 Sidewalks

DescriptionThis project will rehabilitate several high priority sidewalks throughout Wetaskiwin. This year, new sidewalks will also be added at several locations. This is to increase pedestrian access and mobility throughout the City. 
Location(s)
  • New sidewalk along the south side of 40 Avenue from 54 Street to 56 Street
  • New sidewalk along the west side of 47 Street from 40 Avenue to Jubilee Place
  • New sidewalk along the west side of 46 Street from 54 Avenue to 55 Avenue
  • New ramps along 56 Street
  • Several of the worst sections of Willow Crescent
  • Several of the worst Sections of Garwood Crescent
  • Several of the worst sections of 37A Avenue
  • Several other high priority sections throughout the City
Estimated Start DateSpring 2021
Estimate Completion Date Fall 2021
ContractorJ. Branco and Sons Concrete Services Ltd.
Road ClosuresPlease follow all posted signage and use caution when driving through construction zones.
Temporary Utility ShutdownsNo
OtherPlease note that this work will not include an entire replacement of sidewalk, but only priority 1 pieces as defined by the table below. The City must prioritize sidewalk replacement due to limited budget. For sidewalk concerns, please email engineering@wetaskiwin.caand staff will inspect the area of concern. Additional sidewalk work is dependent on priority shown in the chart below, the current years budget and contractor's availability.

Overall Condition

Vertical Separation

Crack Width

Spalled Concrete

Multi-Directional Cracking

Gutter or sidewalk Ponding

Priority

New

5mm or less

6mm or less

5% or less

Little or none

25mm or less

3

Fair

5mm or less

6mm or less

5% to 10%

60% or less

25mm or less

3

Average

5mm to 10mm

6mm to 11mm

10% to 20%

60% to 80%

25mm to 50mm

2

Poor

10mm to 15mm

11mm to 15mm

20% to 50%

80% or more

50mm to 75mm

2

Very Poor

15mm or more

15mm or more

50% to 100%

80% or more

75mm or more

1


Residents can also petition to have their entire sidewalk and roadway replaced through a Local Improvement. More information is available here.

CCTV

DescriptionYou may see the contractors trucks working in your neighborhood cleaning and inspecting underground storm and sanitary infrastructure. The attached map indicates the areas being inspected this year. This work is essential in identifying storm and sanitary issues in order to complete future repairs.
Location(s)

Year 2 Area

Estimated Start DateJune 7, 2021
Estimate Completion Date Fall 2021
ContractorsEmpipe Solutions Ltd.
Yellowhead Inspections
Road ClosuresPlease follow all posted signage and use caution when driving through construction zones.
Temporary Utility ShutdownsNone
Other

55 Avenue

Description55th Avenue was identified as an area in the City that was in need of an underground utility upgrade for water and sanitary. Since the water was determined to be an emergency, the City was forced to begin replacement in the fall of 2020.
Location(s)55 Avenue between Centennial Drive and 51 Street.
Start DateTo be determined
Estimated Completion DateTo be determined
ConsultantAssociated Engineering
ContractorTo be determined
Road ClosuresTo be determined
Temporary Utility ShutdownsTo be determined
Other InformationSo far the eastern half of the water main has been replaced and four water services and sanitary services have been replaced.  

The remaining work will be completed in the spring/summer of 2021, pending council approval. This includes:

  • Replacing the western half of the water main
  • Replacing the sanitary main
  • Replacing all remaining water and sanitary services
  • Surface Restoration

Until all underground work is complete, the City will not be able to pave the road surface.  A temporary gravel surface will be used until all underground utility work is completed.

The remaining work anticipated for 2021 will require excavations in the yards of those homes that have not had service replacements yet.  

2021 Pavement Markings

DescriptionReplacement of existing road markings with inlaid thermoplastic markings. These markings are more durable and come with a 5 year warranty. They are expected to last 10 years.
Location(s)47 Street North of the Train Tracks
49 Avenue between 52 Street and 53 Street
50 Street between 47 Avenue and 50 Avenue
Start DateJune 28, 2021
Estimated Completion DateJuly 6, 2021
ContractorAAA Striping and Seal Coating Services
Road ClosuresSingle Lane Closure- Please use caution when passing work zones
Temporary Utility ShutdownsNone 
Other Information

Public Works Shop Renovation & Addition

DescriptionRenovation and upgrades to the City Public Works Shop
Location(s)5520 - 50 Street
Start DateAugust 12, 2020
Estimated Completion DateSummer 2021
ContractorCreative Infrastructure
Road ClosuresNone anticipated
Temporary Utility ShutdownsNone anticipated
Other InformationWhat is Happening:
Demolishing old storage shed - this creates the space we need for the new shop and office space
Building addition onto existing pole shed - this allows for more indoor storage space
New roof for existing shop and wash bay - this will fix the leaking roofs and allow for extended life of the buildings
Existing shop will be converted to additional storage space
Demolishing old lean-to offices - due to code & safety issues - will become parking or open space

40 Ave & 53 St Traffic Signals

DescriptionThis project will remove and replace the existing traffic signals at 40 Ave & 53 St.
Location(s)40 Avenue & 53 Street Intersection
Estimate Completion Date Spring 2021
ContractorHighLine Electrical Constructors Ltd.
Road ClosuresPlease follow all posted signage and use caution when driving through construction zones.
Temporary Utility ShutdownsNo
OtherMost construction work is completed. Only landscape restoration remains.